For planned and actual costs of plant maintenance and service orders two extractors are available:
- BWSM_PM_GET_ORDCST   / DataSource 0PM_OM_OPA_1
- PMEX_PM_GET_ORDCSTA1 / DataSource 0PM_OM_OPA_2

0PM_OM_OPA_1:
==============
Primarily this DataSource could be used for both, that means for planned and for actual costs (VTYPE = 20 and VTYPE = 10).
Unfortunately this DataSource is not enabled for DELTA load.

0PM_OM_OPA_2:
==============
This DataSource had been designed to extract only actual costs.The result of this extraction is more detailed than the corresponding
result extracted by 0PM_OM_OPA_1 and  due to this customers prefer to use this DataSouce for actual costs.
An additional advantage is, that this DataSource is DELTA enabled.

Because again and again customers had performance problems with 0PM_OM_OPA_1, the decision had been made to optimize 0PM_OM_OPA_1.

In the context of this optimization 0PM_OM_OPA_1 can be used now only for planned costs, but with good performance. and 0PM_OM_OPA_2 for
actual cost extraction .

So please use the DELTA enabled DataSource 0PM_OM_OPA_2 to extract the actual costs of your plant maintenance orders.