Dear All,

I am new to SAP PM Module . I have created 5 Maintenance Strategy & Each strategy containing 15 maintenance packages. Maintenance Plan ( Tcode :--IP01) was created on performance based (9000KM).

Strategy 1 :-- containing Maintenance packages from 9000 to 135000 KM.

Strategy 2:--  containing Maintenance package from 144000 to 216000 KM.

.........................................................................................................................

I want to change the task list of the maintenance Plan as soon as it crosses the boundary of maintenance Strategy 1.i.e. 135000 KM.

System Does not allow me to change the strategy automatically .

Right Now i am creating new plan every time when my equipment crosses the boundary of strategies. 

Kindly Suggest me the right solution ???