Issue:

You want to use the planned delivery time from the info record in the PR. 

Solution: 

In order to use the planned delivery time from the purchasing info record, it is necessary to maintain a source list entry for the material in addition to the purchasing info record.

When a requisition is manually created, the Planned Delivery date will always be taken from the material master.

The date is the delivery date taking into account the

  • planned delivery time in the material master record
  • purchasing department processing time from the materials planning

The planned delivery time from the purchasing info record and the GR processing time are only taken into account if the purchase requisition was generated via the materials planning and control system.