Skip to end of metadata
Go to start of metadata

How can SAP ECTR interface to NX 5.2 be installed with SAP ECTR 1.1 in parallel to an existing SAP ECTR 5.1 installation with SAP ECTR interface to NX 5.1?


A parallel installation of SAP ECTR interface to NX 5.2 is only possible with the creation of a separate installation package for the SAP S/4HANA component.

Therefore, you need to unpack the installation package of SAP ECTR interface to NX 5.2.

Afterwards, delete all SapECTRNX files in XML and CFG format that are not relevant for SAP S/4HANA from the subdirectory Setup.


Finally, create a installation package with the SAP Installation Server. This package can then be used for parallel installation.
In the file SAP Setup Guide.pdf, all necessary steps for using the SAP Installation Server are described.
This guide is included in the installation package of SAP ECTR interface to NX 5.2 and after unpacking, it can be found in the main directory.
The SAP Installation Server is included in the subdirectory Setup.

Please note that despite the settings for SAP S/4HANA, the program registration in Windows for SAP ECTR interface to 5.1 disappears, while the installation of SAP ECTR interface to NX 5.1 is not changed.
Also with a deinstallation of SAP ECTR interface to NX 5.2, the directory of the 5.1 installation does not change. If you want to delete this directory, it needs to be deleted manually.



  • No labels