Purpose
The purpose of this document is to give an overview on the transition from SAP ECTR on SAP ERP to SAP ECTR for S/4HANA.
SAP ECTR brings besides the JAVA client an Add-On on top of either SAP ERP or SAP S/4HANA. This ABAP Add-On is not modifying and is handled with SUM during the upgrade process.
The overall transition process from SAP ERP to SAP S/4HANA can be found on help.sap.com for SAP S/4HANA → Conversion Guide.
Technical transition to SAP ECTR for SAP S/4HANA
The technical transition from SAP ECTR (on ERP) to SAP ECTR for S/4HANA is part of the overall transition from SAP ERP to SAP S/4HANA.
Only for customers having ECTR 4.x:
There is also a ECTR version before 5.x which is a pure partner product, not sold/supported by SAP (also call "legacy ECTR" below). The partner product ECTR 4.x is not supported on SAP S/4HANA. Therefore a transition is required from 4.x to 4.6 or 4.7. SAP ERP + ECTR 4.6 / 4.7 or 5.x can be used as starting point to make the transition from SAP ERP to SAP S/4HANA.
Backend - transports / Add-ons | legacy ECTR 4.4 => S/4 | legacy ECTR 4.5/ 4.6 / 4.7 => S/4 | SAP ECTR 5.0 / 5.1 / 5.2 => S/4 |
---|---|---|---|
Change ECTR to 4.6 (See Overview of the "SAP PLM Integration to NX" (legacy ECTR 4.4) upgrade to SAP ECTR 5.1 or SAP S/4HANA) 1 | (X) | ||
Install S4ECTR with SUM 2 | X | X | X |
1 This step is only then needed when the customer likes to work productive with this intermediate software. If yes the change to ECTR 4.6 / 4.7 is needed because of the HDB.
2 The conversion from EhP7 or EHP8 to S/4HANA is usually done with the Maintenance Planner/SUM tool. This tool does recognize that the Add-on ECTR is installed and the Add-on will be correctly handled. In the following steps the entry for "ECTR" and optionally "ECTRWUI" will be removed and the Add-on "S4ECTR" will be installed.
See note 2325172:
....
c) Conversion from ECTR
Alongside the conversion to S/4HANA, no additional manual activities within the SUM process are required for the conversion of ECTR to S4ECTR.
The conversion is possible with the installation package SAPK-100COINS4ECTR. It should always be carried out together with the highest available SP.
Related Documents
- https://blogs.sap.com/2017/04/01/s4hana-system-conversion/
- https://blogs.sap.com/2016/04/22/how-to-decide-between-a-greenfield-and-brownfield-s4hana-transition/
- https://blogs.sap.com/2018/08/21/sap-s4hana-discovery-greenfield-vs.-conversion-overview-webcast-recap
Related SAP Notes/KBAs
SAP Note 2325172: ECTR: Release strategy for ABAP Add-on S4ECTR
SAP Note 2310438: SAP Readiness Check for SAP S/4HANA - Managed System